Entries by Jamie

,

Walk on the Wild Side

On Wednesday 2 October, Tim Melville visited Peak Wildlife Park at Winkhill, near Leek, to carry out a routine structural inspection of the boardwalks and canopies.  The alpacas occasionally showed a little too much interest in nibbling his clipboard, but overall the residents were happy that Tim gave the timbers a clean bill of health!

,

AJS Sponsor Darley Dale Juniors U13s

AJS Structural Design are proud to be sponsoring and providing the new football kit for Darley Dale Juniors U13s for the 2019/20 season. The team kicked off the season in their new kit with a cracking 7-1 win over High Peak Harriers U13s. Good luck from all of us at AJS Structural Design for the […]

,

Progress on Renovation and Barn Conversion

AJS Structural Design have been providing structural design services for a barn conversion in Tansley which has been split into 2 phases. Phase 1 sees the renovation of an existing dwelling, with the removal of load baring walls to create a new kitchen and living space. Phase 1 is progressing very well as seen in […]

,

Works for New External Yard Commences

We called in to one of our projects in the Derbyshire Dales last week to see how things were progressing. It was good to see levels being formed to stone base nearing completion in preparation for the concrete slab to be cast. The project brief was to provide a new access and concrete external yard […]

,

Attenuation Tank Installation in Derby

Fantastic to see the Triton Attenuation Tanks being installed during a site visit to one of our larger projects in Derby. For this particular project, AJS Structural Design have provided services for the drainage, external and structural design. Looking forward to seeing this one progress further.

,

Steel Work Progressing at Barn Conversion

AJS Structural Design have been working on a grade 2 listed barn conversion in Croxden which is being converted into two new dwellings. The work entails structural support to reinstate the roof and floor structure and a new steel framed sun room and veranda to the rear of the property which can be seen in […]

,

Final Unit Goes Up at Raynesway

The Steelwork of the final unit at Raynesway, Derby has been erected this week. This unit will complete the delivery of over 11,000m2 of industrial floor space in phase 2 of a wider development. AJS Structural Design have provided engineering services for structural and civil aspects of the development.

,

Residential Property Out of the Ground

New residential property is out of the ground and progressing well on site at Yoxall. AJS have undertaken the design for the drainage, external hard standing areas, foundations and supporting steel beams on this project. Looking forward to watch this one take shape.

,

Steel Frame Goes Up at Pektron

Good to see that the steelwork has commenced at Pektron’s new R & D facility and is progressing well. AJS Structural Design have provided consultant engineering services for the steelwork, foundation, drainage and external works design on this project.

,

Progress at Pektron

We were pleased to see, during our site visit, that the foundations are nearing completion on the new Pektron R & D Building at Alfreton Road, Derby, ready for the erection of the steelwork.